Placentia Added $340,692 to a Street Rehab Contract. The Extra Work Went Beyond the Original Street Scope.
The amendment raised RJ Noble's contract from $1,972,915.05 to $2,313,607.58 after added excavation, Fire Station 1 asphalt work, and two older drainage repairs.
A verified Placentia Pulse report on the $340,692.53 RJ Noble street rehab amendment, Fire Station 1 paving, deferred drainage repairs, and the 17.3%...